See the evolution of Burswood Point and Belmont Racecourse by Nine News.

 Golden Sedayu was pleased to contribute to a recent Nine News segment focusing on the evolution of Belmont Park Racecourse and the wider precinct as the Burswood Point masterplanned community begins to take shape.  

As the sole developer of Burswood Point, we feel privileged to be able to create Perth’s next urban neighbourhood from the ground up. We are working with world leading design practices to shape a community that draws inspiration from other thoughtfully planned riverfront destinations like Southbank in Melbourne or Brisbane, that the whole of Perth will be able to enjoy. 

Somerset Residences is making its way up through the podium levels, the River and Garden Homes are being delivered by Urbane and C U Building Group respectively, and the DA for the next two buildings is approved. It is an exciting time at Burswood Point. 

We invite you to watch the video, which highlights the vision for the site, the unique location between the river and racecourse, and the continued progress by Golden Sedayu. 

 

We are pleased to report that August marked another month of steady progress at Somerset Residences, with structural works continuing to advance across multiple work fronts.

At the lower levels, basement formwork stripping is now complete and stripping of the Ground Floor is now progressing.

Above ground, core construction is progressing as planned, with the Somerset East Jumpform now reaching Level 2 and Somerset West Jumpform walls now raised. On both buildings, Level 1 is complete and formwork for Level 2 is underway.

FORESHORE LANDSCAPING

Landscaping works are beginning to establish the future public spaces and waterfront experience at Burswood Point.

The team has progressed the commissioning of irrigation infrastructure, including the bore and iron filtration system, alongside the installation of key landscape elements including hard landscaping structures and rock retaining walls.

This framework marks another step in the delivery of Burswood Point’s 2.5-kilometre foreshore, which will become an integral part of the community’s connection to the Swan River, parkland and surrounding amenity.

We are pleased with the continued progress across both Somerset Residences and the wider Burswood Point community, and look forward to sharing further updates as construction continues.

For more regular behind-the-scenes progress, we invite you to follow us on Instagram and Facebook and subscribe to our Youtube channel.

In the meantime, we hope you enjoy watching the latest construction video.

The Golden Sedayu Construction team is pleased to report that July marked another month of strong progress at Somerset Residences, with construction continuing to advance steadily above the ground on the podium levels. The site has become increasingly active, with several work areas progressing at the same time to maintain the project’s momentum.

Throughout the month, the team completed a number of significant structural milestones, including the basement walls, the Level 1 lift and stair cores, and all of the ground floor structure.

Work also advanced onto the mezzanine level, while the installation of precast concrete elements continued to define the building’s form and layout.

We are pleased with the ongoing progress being made at Burswood Point and remain committed to delivering Somerset Residences to the highest standard.

For more regular behind-the-scenes progress, we invite you to follow us on Instagram and Facebook and subscribe to our Youtube channel.

In the meantime, we hope you enjoy watching the latest construction video.

 

With momentum building on site and behind the scenes, we would like to report that May saw Somerset continue to progress well through the structural phase.

Solid progress has been made across both cores (staircase and lift shaft) and the suspended slab works. Somerset East core vertical works continued ahead of the jumpform being erected and Somerset West has been set to have its jumpform installed in June. Jumpforms help with the construction of lift and stair cores when the formwork gets jumped from one level of a concrete structure to the next, thus increasing construction speed and reducing reliance on cranes.

With basement slab works now complete, activity across site has continued to build as the focus shifts further into the above-ground structure. Multiple areas are now progressing, including the formwork, reinforcement works and pouring of the ground floor suspended slab. With more of the structure now visible, buyers will begin to see Somerset’s scale and form emerging over the coming months.

Overall, the project remains on track to the construction program, with close coordination of logistics, crane operations, and follow-on trades continuing to play an important role as works continues to ramp up.

View the May Construction Video.

For frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

 

 

To celebrate the completion of Racecourse Boulevard, Golden Sedayu was finally able to welcome buyers and interested parties to a one-day-only Sneak Peek of Burswood Point, offering an opportunity to experience the scale of the development firsthand.

As a working construction site, this was the first time the site had been open to the public and the response was incredible. It was wonderful for visitors to immerse themselves in the exceptional location and panoramic views of the Swan River, Belmont Park and Optus Stadium

Driving down the boulevard, it’s easy to visualise the future vibrancy of the neighbourhood, which will be enhanced by the internationally acclaimed 5-star Anantara Resort, retail and dining precincts, entertainment offerings, expansive public open space and riverfront parklands.

If you missed out on the SNEAK PEEK, we invite you to view a short video of the event.

 

To climb the scaffold and experience the incredible Burswood Point offering for yourself, please visit www.burswoodpoint.com.au

For frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

We’ve seen strong progress at Burswood Point this month, with construction advancing across Somerset Residences, the Garden and River Homes, as we near the completion of Racecourse Boulevard in May.

Somerset has now moved into the vertical construction phase, with bulk excavation nearing completion, both cores underway, and major foundation elements, including the Somerset West basement slab, now poured.

CU Building Group has poured the suspended first floor slabs for Stage 1 of the Garden Homes, with structural steel installed and brickwork now underway. Formwork is progressing for the remaining homes ahead of upcoming slab pours.

Momentum continues across the River Homes, with ground floor slabs completed, structural steel installation imminent, and brickwork underway for Stage 1. Urbane Projects Pty Ltd has also completed documentation for Stage 2, ready to lodge the Building Permit applications with the Town of Victoria Park in May.

This level of concurrent progress highlights the scale and coordination behind Burswood Point, as it continues to take shape as one of Perth’s most significant new waterfront communities.

For frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

 

It was a privilege for the Golden Sedayu team to be invited to participate in The Urban Developer’s inaugural Perth Symposium on March 11 and 12.

The event brought together 150+ senior property professionals, including private and institutional developers, investors, financiers, consultants and government stakeholders. The program explored investment conditions, supply and demand dynamics, planning and infrastructure, and where the next wave of opportunity sits across Greater Perth.

On Day 1, our Managing Director Andrew Sugiaputra and Development Director Andrew Bouhlas welcomed guests to Burswood Point for two exclusive site tours of our display suite and broader precinct. Attendees had the opportunity to learn more about the 38ha masterplanned community, see the 2.5km stretch of Swan River foreshore – a waterfront that has not been publicly accessible for more than 80 years, and view construction progress firsthand at Somerset East and West, along with the River and Garden Homes.

On Day 2, Andrew S joined the panel discussion Investing in the Future of Perth, sharing insights into why long-term investment in well-planned precincts continues to be critical to Perth’s growth.

For frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

As construction progresses on the boutique riverfront residences at Burswood Point, we are pleased to announce that the site will also be home to Australia’s first luxury Anantara Hotel.

The celebrated Thai-inspired wellness hotel will anchor our 38 hectare masterplanned project and form a key part of the long-term vision for the precinct.

The Anantara brand is part of the leading global hotel owner and operator Minor Hotels’ portfolio, which spans over 640 hotels, resorts and branded residences across the world. Its launch into Burswood Point reflects growing confidence in the scale, location, design and international appeal of the project.

This partnership reinforces our long-term vision to deliver a thriving, well-serviced community that integrates high-quality residences, hospitality, retail and public amenity at Burswood Point. The landmark luxury hotel will be defined by exceptional design, craftsmanship, and service.

We see this interest from a globally recognised luxury operator of this calibre as a strong endorsement of the masterplan design concept by Skidmore Owings and Merrill (SOM), and the progress of the premium residential product currently under construction.

The hotel will feature 150 contemporary guest rooms and suites, two destination restaurants, a swimming pool, and a fully equipped fitness centre. An Anantara Spa will introduce Perth to the brand’s award-winning approach to wellness with indulgent, publicly accessible amenities.

We’ll continue keep you updated on our progress, but for more frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

Golden Sedayu is proud to be recognised in various high-profile categories in this year’s Business News Book of Lists.

The annual publication is widely anticipated for its data and insights highlighting the success of Western Australian entrepreneurs, executives and industry leaders across a range of sectors.

This year, the $4 billion Burswood Point masterplan ranked in the Top 10 Major Projects category, based on construction cost.

Somerset Residences – the first two premium towers at Burswood Point – also ranked No. 6 in the Built-form Developers category, based on the total value of WA projects currently under construction ($423 million).

Recognition such as this is a reflection of the hard work, talent and vision of the Golden Sedayu team and our project partners.

We look forward to bringing you more news on our achievements and milestones, but for more frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

 

 

We’re pleased to welcome you into the new year with an exciting update from site.

Golden Sedayu Construction has maintained strong momentum over the festive period, with the successful installation of the tower crane for Somerset East. The erection of the crane marks a key milestone for Burswood Point, signalling the vertical commencement of the first building within the broader 38-hectare masterplanned community. View the drone video here.

At Somerset East, the basement slab is currently undergoing waterproofing and preparation works in readiness for the next stage of structural pours, while excavation works continue at Somerset West down to the required basement pad level.

Once the second tower crane is erected next month, basement slab works will continue through to Somerset West, enabling construction to progress concurrently across both buildings.

We’ll continue keep you updated on our progress, but for more frequent and visual updates, we encourage you to follow Burswood Point on Instagram and Facebook.

We’re also pleased to advise completion remains on track for Q4 2027.

 

 

 

 